Lloyd Project
Home Park District Info Plans + Projects Waterfront 2030 Lloyd Project
Park District Info
Location
Winnetka Park District
Admin + Recreation Office
540 Hibbard Road, Winnetka, IL 60093
P: (847) 501-2040
F: (847) 501-5779
E: wpdinfo@winpark.org
Hours
Monday – Friday: 8:30am – 5pm
About The Waterfront 2030 Plan
In conjunction with residents and lakefront experts, the Winnetka Park District developed and adopted the Winnetka Waterfront 2030 plan in 2016. This plan is meant to serve as a conceptual guide for future projects that preserve and enhance our five beaches.
Lloyd Project
Cost
Altogether, this project cost approximately $5.1M and was paid for using a mix of revenues, reserves, and alternative revenue bonds.
Projects
Beach replenishment content coming soon.
Bluff restoration efforts were completed at Lloyd in two phases from 2017 to 2021. Maintenance of the new bluff vegetation will be ongoing for the next three years.
Phase 1: Bluff restoration in the upper park area (removed invasive vegetation, planted new native vegetation, conducted controlled burns)
Phase 2: Bluff restoration in the lower park areas and new retaining wall (reinforce against erosion, plant native vegetation)
New boardwalk extending from the beach house to the parking lot.
Boat launch repaving
To learn how breakwater systems work, click here.
PROGRESS UPDATES
July 21, 2020
Construction officially kicked off last week for the new breakwater system at Lloyd Beach! So far, 2,500 tons of materials have been delivered and contractors have begun building the foundation for the breakwaters. Check out the video above to see the progress. Over the next several months, 20,000 more tons of rock and sand will be delivered to build the new breakwaters and reinstall the beach. Construction is expected to wrap up by the end of the year. View timelapse video.
August 5, 2020
The south breakwater is starting to form. Construction materials continue to arrive daily via truck and barge. So far the barge has delivered a few thousand tons of armor stone, reducing the number of semi-truckloads driven through the community. Check out the video to see the progression since our last update! View timelapse video.
August 28, 2020
The south breakwater continues to take shape and the breakwater on the north end is almost complete. Check out the video to see the progress since our last update! View timelapse video.
September 18, 2020
The north breakwater is complete and contractors have started on the middle breakwater island. To build the island, they’ve had to make a temporary road from the shoreline to the breakwater. This road will be deconstructed once the island is complete. In the past two weeks, more than 8,000 tons of sand have been delivered to rebuild the beach — there’s actually a beach now! Check out the video to see the progress since our last update. View timelapse video.
September 29, 2020
The contractors have made significant progress on the middle and south breakwaters and continue to deliver sand daily to build up the beach. We are on schedule to complete work by the end of the year and can’t wait to see you for a great 2021 season! This week’s video is a drone flyover of the beach. View the flyover video.
For progress pictures, see the photo gallery below.
October 23, 2020
The breakwater project is nearing 90 percent completion, with work just remaining on the south breakwater arm. This week’s video shows you the view from the beach so you can get an idea of how tall the structures are. View the video.
November 30, 2020
The breakwaters structures are 100 percent complete. The contractor will remain on-site for the next few months to dredge, regrade the beach, etc. All work will be complete by the 2021 boating season.
For progress pictures, see the photo gallery below.
April 1, 2021
The new breakwaters did an awesome job protecting Lloyd through the winter. The beach is in great shape and very little sand was lost. Contractors remain on-site, currently building the new boardwalk and access ramp. Bluff and pavement work will start in April, followed by the installation of boat storage racks south of the beach house. All work is expected to wrap up by May 15. View the flyover video.
Fenced-in motorized boat storage renovations.
New / relocated non-motorized boat racks to the south beach.
Pier content coming soon.
South beach access ramp improvements.
Project Status
Project | Status |
---|---|
Beach Replenishment | Complete |
Bluff Restoration | Ongoing |
Boardwalk | Complete |
Boat Launch Repaving | Complete |
Breakwater System | Complete |
Fenced-In Motorized Boat Storage | Complete |
Non-Motorized Boat Racks | Complete |
Pier | Not Started |
South Beach Access Ramp | Complete |
Lloyd Photos
Lakefront Information
Board Meetings
Lakefront projects may be discussed during board meetings. View board meeting agendas and minutes by clicking the button below.
News
View all News posts regarding our lakefront by clicking the button below.
Lakefront Videos
Click the button below to view all videos regarding lakefront news, updates, and flyovers.
Bluff Restoration + Shoreline Stabilization
Bluff improvements and shoreline stabilization are crucial to protecting our lakefront. If you would like to learn more, please click the button below.